GALANTAS HIGHLIGHTS IRISH GOLD PROJECT ACTIVITIES

 

Galantas Gold Corporation (“GAL” – TSX-V) is pleased to provide highlights of development and exploration on its County Tyrone gold project since closing the equity placement for $3,503,333 ($3,279,283 net of financing costs) in April.

  1. On May 2 nd, construction manager, Mr. Steve Higgins, was appointed.
  2. Building Control Regulations and IPPC (Industrial Pollution Prevention and Control) applications were submitted.
  3. Detailed engineering of tailings facilities and water management system was initiated.
  4. Paste tailings rheology study was conducted.
  5. Plant layout and process mass balance calculation was finalised .
  6. Grinding, flotation, pressure filter and thickener equipment was sourced and ordered.
  7. On May 27 th, Barclays loan facility for excavators and dump trucks was put in place.
  8. On June 20 th, 2 excavators and 2 dump trucks were delivered to site.
  9. On June 10 th, an archaeologist was engaged to prepare a dig plan and oversee initial site excavation, a requirement throughout Ireland.
  10. In July, acoustic and dust monitoring and abatement programmes were put in place.
  11. In August, overburden removal was begun at Kearney Pit. Site preparation of

the tailings facility, water management facility and plant site are scheduled this month.

In addition to these project development items, a revitalised exploration programme over the Company’s Prospecting Licence in County Tyrone was begun. A helicopter-borne VTEM (electromagnetic) survey was completed. Currently, the airborne survey results are being interpreted and integrated with other exploration data.

In advance of designing a follow-up exploration programme, check sampling of glacial till and stream-bed boulders is being carried out. The results of this sampling will assist in the interpretation of the extensive data base mainly developed during Riofinex’s ownership of the Licence in the 1980’s. It is noted that the sources of many strong geochemical anomalies in this overburden covered area have never been discovered.

Galántas Gold Corporation is building Ireland’s only gold mine on its 189 sq km exclusive Prospecting Licence. The corporate aim is to increase the approx 447,000 oz gold resource on the property through exploration and mine development, to expand mine production in stages, and to add value to the Company’s production by marketing and selling certified Galántas ™ Irish gold jewellery.

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the contents of this news release. This press release may include certain “Forward-Looking Statements” within the meaning of the US Private Securities Reform Act of 1995. Other than statements of historical fact, all statements are “Forward-Looking Statements” that involve such various known and unknown risks, uncertainties and other factors. There can be no assurance that such statements will prove accurate. Results and future events could differ materially from those anticipated in such statements. Readers of this press release are cautioned not to place undue reliance on these “Forward-Looking Statements”.

For further information, please contact:
Jack Gunter -- Executive Chairman
Roland Phelps -- President & CEO
Moe Lavigne -- Vice President
Telephone: +44 (0) 2882 241100
Email: info@galantas.com Website: www.galantas.com
 
o

You can return to the Top of this page